Remove the siding. Expose the band joist.

Step 1. Remove the siding. Expose the band joist.

Remove the siding or cladding and expose the home’s band joist. Connecting through siding—even if it’s brick veneer or stucco—is a no-no. By the way, I use this little Dremel saw more often than I ever would have thought. It was excellent for cutting vinyl.

build a deck
Apply peel and stick membrane to the band joist.

Step 2. Apply peel and stick membrane to the band joist.

Even though I’ll add rigid metal flashing later in the process, I want there to be a 0.0% change water can get to the house’s band joist. So, I add a flexible flashing. In this case a rubberized peel and stick membrane.

build a deck
The Prescriptive Deck Code says the door shall be flashed AND caulked.

Step 3. Caulk under the door and over the flashing to seal it all together.

build a deck
Mark joist locations on the ledger and beam together.

Step 4. Mark joist locations on the ledger and beam together.

When I build a deck I cut the ledger and beam to the deck’s overall width first. Then, I mark the joist locations on the ledger board and the beam at the same time. This saves a potential mistake later.

build a deck
Cut 1 1/2-inches off each end of the ledger.

Step 5. Cut 1 1/2-inches off each end of the ledger.

Then, in order to accommodate band joists to be installed later I cut 1 1/2-inches off each end of the ledger. Cutting 3-inches off one end shifts the layout. This is pretty important. Go through all the steps.

build a deck
I always check the door for level and layout the ledger from a low corner—if it has one.

Step 6. Check the door for level 

I use two levels when I build a deck—a spirit level for determining if the door is level or not and a laser level to establish the overall level line for the ledger board.

build a deck ledger board myfixituplife
Snap a line 2-inches in from each edge of the ledger.

Step 7. Snap a line 2-inches in from each edge of the ledger.

Code requires the fasteners to be installed in an up-down pattern, usually two in each joist bay. Code also wants fasteners 2-inches in from each edge of the board.

To minimize measuring and the risk of overlapping metal hardware with screw locations, I snap a line on the ledger and mark fastener placement.

I use 5/16 x 5-inch Spax Power Lags. With serrated tips and unbelievably strong pull-out power. With their washer head, they’re my go-to fastener for ledger boards, pergolas, and other structural connections.

build a deck ledger board myfixituplife
Spax Power Lags serve as mighty cleats for helping to set the ledger.

Step 8. Use Power Lags as cleats

I use Power Lags as cleats to help me install the ledger accurately. Snug one about 2 inches deep on each end of the ledger location between the mudsill of the house and the foundation. I lift and rest the ledger board on them. Then, once placed, I can adjust it to proper location and fasten. This is a huge help in positioning the ledger accurately on the layout line.

build a deck ledger board myfixituplife
Spax Power Lags installed two per joist bay, top-left, bottom-right. No extra tools required.

No pre-drilling and no washers or ratchet sets. Just full-tilt boogie getting these installed. I used the uber-awesome Spax Power Lag as my primary fastener for installing the ledger. I use two per joist bay and zing them in with the impact driver I’m using to install everything else.

build a deck
Metal flashing goes above the ledger and under the first deck board to divert water.

Step 9. Metal flashing goes above the ledger

Rigid metal flashing above the ledger and below the first deck board—extending out past the the deck board edge—is required, too.

While there are various flashing items for sale, I make mine on the sheet metal brake, because, well, I have a sheet metal brake.

build a deck
Note the flashing along the front edge of the first deck board by the house. OK, and my smile. Happy to be putting down boards.

One more thing…

build a deck how to attach the ledger board
Use a temporary stand-off to help place the ledger accurately.

Quick carpentry tip.

When I build a deck I often use blocks, cleats, site-made gauges or some other means of placement other than a tape measure. In this case, I screwed a block to the end of the ledger before installation. Now I know that when I install the band joist—made of the same material—it’ll fit in the opening created by the block.

If you haven’t watched the video, here it is. Good luck. If you have more questions about attaching the ledger board, send me a note or share a comment below.

Related Posts

Leave a comment

Verified by MonsterInsights